Basement finishing turns concrete walls and an open ceiling into rooms that feel like the rest of the house. In Des Moines, the order of the work matters as much as the materials, because the city has to see the framing and wiring before anything gets covered. If the basement leaks or stays damp, have that fixed before any framing goes up.
A typical sequence
- Plan the rooms. Decide what goes where, and whether any room will be used for sleeping. A bedroom changes the window requirements (see below).
- Get the permits. A building permit covers the framing and finish. Electrical, plumbing and mechanical work each need their own permit when they're part of the job [1].
- Frame and rough in. Walls, wiring, ductwork and any drain lines go in.
- Inspect before covering. Des Moines doesn't allow permitted work to be concealed until the building official has inspected and approved it [2]. Once the applicant is told inspections need to be scheduled, they have ten days to book them [1].
- Insulate, hang drywall and finish. Ceilings, trim, flooring and paint come last.
- Final inspection. The permit isn't closed until the work passes.
Rules worth knowing in Des Moines
- Bedrooms need an egress window. The city's policy says an existing basement finished with a bedroom must have an egress window in that bedroom. A finish without a bedroom doesn't need one [3]. Our egress page has the sizes.
- Smoke alarms. The city's smoke alarm handout says that when interior alterations need a permit, or a bedroom is added, the home gets smoke alarms placed as they would be in a new house, interconnected and hardwired. There's an exception when the work doesn't remove wall or ceiling finishes [4]. The 2024 code amendments also say that a newly installed battery smoke alarm must run on a sealed battery that lasts at least ten years [5].
- Low ceilings. The 2024 code the city enforces calls for 7 feet in basement living space, with beams and ducts allowed down to 6 feet 4 inches [6]. The city's egress policy also treats a basement under 6'-8" as one that may not be finishable [3].
- Doing your own trade work. If you live in the house and it's your homestead, you can apply for the electrical, plumbing or mechanical permit yourself, and the city may test you first [1]. Iowa also doesn't require an electrical license for an owner working on their own existing single-family principal residence that qualifies for the homestead tax exemption, but inspections are still required for new electrical installations [7]. A similar plumbing exemption is in Iowa Code section 105.11; local permit and inspection rules can still apply [8, 9].
Hiring basement finishing contractors
Iowa law requires construction contractors who earn at least $2,000 a year from construction to register with DIAL. The state's definition of construction is broad and includes carpenters, electricians, plumbers and painters [10]. Ask for each company's registration number.
In Des Moines, electrical, mechanical and plumbing permits are issued in the name of the contractor and the contractor's business [1]. Ask who will take out each permit, and get that in writing with the quote.
When you compare bids, make sure each one prices the same rooms, the same ceiling type and the same number of outlets and lights. One quote that leaves out permits or the egress window isn't cheaper. It's incomplete.
What it costs
HomeGuide's national range is $30 to $50 per square foot to finish a basement [11]. Des Moines charges $154.50 for a residential renovation building permit and $77.25 each for electrical, mechanical and plumbing permits on alterations to an existing home [12]. See the cost guide for more.
Next
If the basement is already finished and you want it redone, read basement remodeling. To get a contractor's price, use the request form.
We're a referral service, not a contractor, and independent contractors may pay us for referrals.
Sources
- City of Des Moines Ordinance No. 15,861, Chapter 26 Secs. 26-136, 26-301 and 26-302 (passed Feb 10, 2020) https://councildocs.dsm.city/ordinances/15861.pdf
- City of Des Moines Ordinance No. 15,597, Chapter 26 Secs. 26-135 and 26-153 (passed July 24, 2017) https://councildocs.dsm.city/ordinances/15597.pdf
- City of Des Moines, Basement Egress Window/Emergency Escape Opening Policy (PDF, updated 5-22-2014) https://www.dsm.city/Documents/Departments/Development%20Services/Permit%20Development%20Center/Residential/Residential-Basement-Egress-Window-Policy.pdf
- City of Des Moines, Residential Smoke Alarms handout (PDF, revised November 2013) https://www.dsm.city/Documents/Departments/Development%20Services/Permit%20Development%20Center/Residential/Residential-Smoke-Detectors.pdf
- City of Des Moines Ordinance No. 16,520, adopting the 2024 IRC with amendments (passed Dec 8, 2025) https://councildocs.dsm.city/ordinances/16,520.pdf
- International Code Council, 2024 International Residential Code, Section R313.1, adopted by City of Des Moines Ordinance No. 16,520 (passed Dec 8, 2025) https://codes.iccsafe.org/content/IRC2024V1.0/chapter-3-building-planning
- Iowa Department of Inspections, Appeals, and Licensing, Electrical Licensing FAQs (fetched Nov 11, 2026) https://dial.iowa.gov/licenses/building/electrical-licensing/electrical-licensing-faqs
- Iowa Code section 105.11, Exemptions (2026) https://www.legis.iowa.gov/docs/code/2026/105.11.pdf
- Iowa Department of Inspections, Appeals, and Licensing, Plumbing Licensure (fetched Nov 11, 2026) https://dial.iowa.gov/licenses/building/plumbing-mechanical/plumbing-licensure
- Iowa Department of Inspections, Appeals, and Licensing, Contractor Registration (fetched Nov 11, 2026) https://dial.iowa.gov/licenses/building/contractors
- HomeGuide, "How Much Does It Cost to Finish a Basement? (2026)," February 6, 2026. https://homeguide.com/costs/cost-to-finish-a-basement
- City of Des Moines Permit and Development Center, Permit Fees, New Fees 1-1-26 (PDF) https://www.dsm.city/Documents/Departments/Development%20Services/Permit%20Development%20Center/PDC%20Permit%20Fee%20Schedule.pdf